On Monday 12 August 2013 05:18 PM, Senthil Kumaran S wrote:
> Let us say we have 5 panda devices. A multinode job requests for 5 panda
> devices and we have accepted this job since we know there are 4 devices
> available in the lava instance. There are 5 CI jobs which are running

Let us say we have 5 panda devices. A multinode job requests for 5 panda
devices and we have accepted this job since we know there are 5 panda
devices available in the lava instance.

I meant to say the above in my previous comment.